Set Up in 6 Easy Steps

Step 1

Your Mandala designer will create detailed foundation drawings and guide your contractor through the set-up process. Once your foundation is complete (provided by others), assemble the pre-cut flooring pieces supplied in the Mandala Home kit.


Step 2

Stand and brace the perimeter walls.


Step 3

Stand and brace the central ring and platform. This is ideally done using a boom truck or crane (as shown), but on smaller homes can be done by hand with four guys.


Step 4

Assemble the engineered truss roof system and apply the pre-cut plywood roof sheathing.


Step 5

Attach the pre-assembled soffit panels and the pre-cut corner trim and fascia.


Step 6

Install the roofing material (not supplied), install the skylight, and hang the exterior doors.

WEATHER TIGHT SHELL IS COMPLETE!